ç Back to Photo Gallery Main Page
space frame designs

INDUSTRIAL  -  CHILE COPPER  -  ARGENTINA GOLD  -  CANADA COAL

Industrial Stockpile Enclosures & Tank Roofs
 

Click on picture for larger view

Triodetic space frame structures offer a competitive solution for long span stockpile enclosures and for tank roofs in bulk materials mining, processing & terminal facilities. Triodetic space frame design domes, composite shapes, & longitudinal enclosures are available in Galvanized Steel, Stainless Steel, Aluminum, Timber & Polycarbonate to suit almost any structure size, load or corrosive environment.

 

ñ Back to top
 

Copper Ore Stockpile Enclosure, Escondida, Chile
 

Click on picture for larger view

Toroids for 200' x 500' enclosure (160,000mt)
Span
: 60m (200ft), Rise: 30m (100ft)
Seismic Zone 4
Owner: Minera Escondida Limitada (MEL)
Project Partners: BHP Billington, Duke
Power, Fluor Daniel Chile, Bechtel,
Yolles, Cade-Idepe Montayes Delta
Limitada, Santiago Chile

Spaceframes and Space frame designs Spaceframes

Space frame design architectural structureSpaceframesStockpile material is deposited via the 8m x 9m roof gantry along the crown of the structure. These severe line loads & dynamic forces are transmitted to the foundations via 14 lateral steel arch trusses spaced 12m apart. The design allows for any single truss becoming ineffective in the event of equipment malfunction. Triodetic framing between the trusses is designed as a series of curved single layer shells (toroids) spanning 200ft x 50ft and rising to 100ft at the roof apex. The frame sections were all pre-assembled at ground level & sequentially positioned with stand-off brackets to accept linear horizontal purlins, curved decking & translucent panels. The end walls are designed as vertical two layer space frames & were installed as two pre-assemblies. The walls require no intermediate foundations & can be re-located in their assembled state in the future when the stockpile & building length are extended. Other advantages of the Triodetic solution beyond the prime purpose of dust suppression, included avoidance of scaffolding & working at height, reduced foundation loads versus an A-frame building alternative, added space for material handling equipment, and an efficient construction sequence that held this activity off the project critical path. 

ñ Back to top
 

Veladero Gold Mine Dome, San Juan Argentina
 

Click on picture for larger view

Spaceframes Technology

DOME Stockpile Enclosure
Owner
: Minera Argentina Gold S.A.
Engineer: SNC Lavalin, Toronto
Diameter: 50m (150ft),
Rise: 27m (80ft)
Designed for seismic IV,
unbalanced snow & 145mph wind loads

Spaceframes Dome in San Juan Argentina

This dome space frame design covers a gold are stockpile for a 36,000 t/day processing plant, 380 km north west of San Juan Argentina in the Andes mountains at altitude 4100m (13450ft) above sea level. Dome materials were available on site commencing 10 weeks after drawing approvals. Construction was completed in less than 5 weeks by local crew of 10 under the direction of a Triodetic supervisor.

ñ Back to top
 

Fording Coal Thickeners
 

Click on picture for larger view

Dome Spaceframe Assembly

Dome Roofs
Owner
: Fording Coal, B.C.
Engineer: SNC-Lavalin, Edmonton
Fording River: 52m (171ft) dia.
Greenhills: 50m dia (160' x 44'h),
30m dia (100' x 27'h)
Cladding: Curved Corrugated deck
with tapered cover panels

Aluminum spaceframes

Safety nets were used under the dome space frame assembly to allow Fording operations to continue uninterrupted. To accelerate construction, each dome was assembled in two halves - as an annular ring on tank wall & crown caps for the 50m & 30m dia domes (15000 & 5000lbs) were assembled separately, lifted to position & connected to their base rings. Domes were designed for 110psf unbalanced snow load and reactions at the base perimeter were no more than 10kips horizontally & 25kips vertically at each of the 64 footing attachment points for the larger dome. These forces were approximately half these values on the smaller dome. Frame assembly with a crew of 3-6 men was completed in around 5 weeks, once panel installation commenced a crew of 9 completed the deck in 10 days.
Spaceframes

ñ Back to top

ç Back to Photo Gallery Main Page

TRIODETIC*© 2007

Home     |    Who We Are     |     Products     |     Media Centre     |     Photo Album     |     Contact Us